Construction Loan Draw Schedule: How Draws Work

A construction loan draw schedule explained: requests, inspections, retainage, lien waivers and funding, with a worked example. Know it before you build.

Inspector and builder walking a framed new home in Florida to verify progress for a construction loan draw schedule

Your construction loan draw schedule is the most important document in your build after the plans. It decides when you get paid, how fast you can pay your crew and whether the project finishes on time.

Most investors worry about getting approved. The ones who build well worry about what happens next: how money moves from the lender to the job site. This post walks one draw cycle from start to finish.

Key takeaways

  • A construction loan is not paid out at closing. Funds are released in draws as inspected work is completed.
  • Each draw follows the same cycle: request, inspection, review, funding.
  • You pay interest only on money drawn, not on the full loan amount.
  • Clean paperwork speeds every draw: invoices, photos, lien waivers and an up-to-date budget.
  • Plan your cash flow. You may need to float some costs for a few days between draws.

What is a construction loan draw schedule?

A draw schedule breaks your budget into stages. Each stage maps to line items in the budget, and the lender releases money for a stage once the work is done.

Think of it as a pay-as-you-go system. The lender never hands you $400,000 and hopes for the best. It funds the foundation when the foundation is poured, the framing when it is framed.

That structure protects the lender, and it protects you. It keeps the loan balance in line with the value in the ground, and it keeps your interest bill low.

A sample construction loan draw schedule

Here is an illustrative schedule for a $400,000 construction budget. Your lender's schedule will differ.

Draw
Stage
Budget released
Cumulative
1
Site work, permits, utilities
$40,000
$40,000
2
Foundation / slab
$50,000
$90,000
3
Framing and roof
$80,000
$170,000
4
Windows, doors, rough MEP
$70,000
$240,000
5
Insulation, drywall, exterior
$60,000
$300,000
6
Interior finishes, cabinets, flooring
$65,000
$365,000
7
Final completion, CO, punch list
$35,000
$400,000

The final draw is often the one lenders hold until a certificate of occupancy (or the local equivalent) and a final inspection are in hand.

How a draw works, step by step

Step 1: Finish the work

A draw covers work that is done. Not planned, not purchased, not half-finished. If the framing is 60% complete, expect a partial draw or none at all.

Step 2: Submit your draw request

The draw request is your invoice to the lender. It usually includes:

  • The draw form showing which budget lines you are drawing.
  • Contractor and subcontractor invoices.
  • Photos of the work.
  • Lien waivers for work already paid.
  • Any permits or inspection sign-offs from the city or county.

With the RBI Draws Client Portal, you can submit requests, track your budget and see your draw history in one place. A digital request also leaves a record of exactly what you sent.

Step 3: The draw inspection

A draw inspection confirms that the work in the request exists and is done to the stage claimed. An inspector visits the site, compares what they see with the budget and takes photos. They check that the percentage complete roughly matches the amount requested.

Inspectors are not building inspectors. They do not approve the work for code. They tell the lender whether the money matches the progress.

Tip: be on site or have your superintendent there. Open the house, clear access and have the budget handy.

Step 4: Review and title

After the inspection, the lender reviews the report against the budget. In many programs, title is updated to confirm no new liens have been recorded on the property. If a subcontractor has filed a lien, the lender needs it cleared before it releases more money.

Step 5: Funding

When everything lines up, the lender wires the approved amount. Funds typically go to you or to your title company, depending on the loan documents. You then pay your contractor and subcontractors, and collect lien waivers for the next draw.

Retainage and lien waivers

Two terms trip up first-time builders.

Retainage is a percentage of each payment withheld until the work is finished. Some contractors and lenders use it, others do not. If your contract includes retainage, build it into your cash flow, because it changes how much you pay on each draw. Ask your loan officer how the loan handles it.

Lien waivers are signed statements from your contractor and subs saying they have been paid and give up the right to file a mechanic's lien for that work. They protect the property, the lender and you. Collect them with every payment, not at the end. Chasing a waiver three months later is miserable.

State laws on liens and waivers differ, so talk to your attorney about the forms that apply in your state.

What a draw really costs

You pay interest only on funds drawn, which is why this structure is called non-Dutch interest in private lending. If you have drawn $90,000 of a $400,000 loan, your monthly interest is calculated on $90,000.

Using an illustrative market-range rate of 12% (the Crestmont Capital June 2026 survey puts ground-up construction loans at 11% to 15%; this is not an RBI quote):

Balance drawn
Monthly interest at 12%
$90,000
$900
$240,000
$2,400
$400,000
$4,000

That gap is a real saving. Compare it with paying $4,000 a month from day one on a fully funded loan. A per-draw fee and inspection cost may also apply, so ask for them in writing and add them to your budget.

Cash flow: the part people miss

Draws are reimbursement-style. You do the work, then you get paid. That means you must plan for float.

  • Keep a cash buffer for the first weeks of each stage.
  • Negotiate payment terms with your contractor to match the draw cycle.
  • Request draws as soon as a stage is done. Do not stack up three stages and request them together.
  • Keep your budget updated. Move line items only with your lender's approval.

Most draw delays come from the borrower side: missing waivers, photos that do not match the request, or invoices that do not tie to the budget. They are all fixable before you submit.

Common draw problems and fixes

Problem
Fix
Inspector finds less work than billed
Request only the percentage complete
Missing lien waiver
Collect it with each payment
Cost over the budget line
Ask for a budget reallocation before you submit
Lien on title
Have the sub release it, then re-submit
Slow request
Send photos, invoices and waivers together

For a lender's-eye view of how this works inside RBI, see our post on construction financing and draw management and our announcement of the RBI Draws Client Portal.

Build a draw-friendly budget before you apply

A good schedule starts with a good budget. The U.S. Census Bureau's monthly new residential construction data shows how volatile builder activity can be. Costs and timelines move, so your budget should too.

  • Break the budget into line items that match the construction stages.
  • Add a contingency line (more on that in our post on spec-build budgets).
  • Ask your contractor to price each stage separately.
  • Share the schedule with your loan officer before closing.

Our investor FAQ answers more questions on loan structure.

Frequently asked questions

What is a construction loan draw schedule?

It is the plan for releasing loan funds in stages as work is completed, tied to the line items in your budget. Each stage, or draw, is paid after the lender confirms the work is done.

How many draws does a ground-up build usually have?

Most ground-up projects use five to eight draws, from site work and foundation through framing, mechanical systems, drywall, finishes and final completion. The exact number depends on the budget and the lender.

How long does it take to get a draw funded?

It depends on how quickly the inspection is done and how complete your paperwork is. Submit clear photos, invoices and lien waivers with the request, and ask your loan officer what turnaround to expect.

Who pays for the draw inspection?

Draw inspections and draw fees are usually a borrower cost, set out in the loan terms. Ask your lender for the fee structure before you close.

What is retainage on a construction loan?

Retainage is a percentage of each contractor payment held back until the work is complete, so the contractor has a reason to finish. Practice varies by lender and by contract, so confirm it in writing.

What happens if a draw request is rejected?

The lender explains what is missing or incomplete, you fix it, and the request is re-submitted. Rejections are usually about paperwork, work that does not match the budget line, or a missing lien waiver.

Draws released as the build progresses

At RBI, you work with a real loan officer, and we fund with our own capital as a direct lender. Draws are released as the work is completed, and you can follow them through the RBI Draws Client Portal. No handoffs to a servicer you have never spoken with.

Get your terms to see how a draw schedule would look on your next ground-up build, or read about our construction loan program.

This is not an offer for extension of credit nor a commitment to lend. Programs, rates, terms, and conditions subject to change without notice. Certain restrictions may apply. All approvals subject to underwriting guidelines. Not all applicants will qualify. RBI Private Lending LLC provides business-purpose loans only. NMLS #2609886.